![SNT Energy Completes HRSG Supply for 290-Megawatt LNG Plant [CAPTIONS]
Key officials including SNT Energy CEO Shin Kyung-in (first from left) pose for a photo at the completion ceremony for HD Hyundai E&F's Daesan LNG power plant, held on Nov. 14 at HD Hyundai Oilbank's Daesan plant in Seosan, Chungcheongnam-do. Photo courtesy of SNT Energy - Seoul Economic Daily Society News from South Korea](https://wimg.sedaily.com/news/cms/2026/09/14/news-p.v1.20260914.646a380330ba486db691ada345c9b6af_P1.jpg)
CHANGWON — A 290-megawatt liquefied natural gas district energy plant equipped with heat recovery steam generators (HRSG) supplied by SNT Energy is set to begin operations in Daesan, Seosan, in South Chungcheong Province.
SNT Energy said on the 14th that it attended the completion ceremony for HD Hyundai E&F's Daesan LNG district energy project, held at HD Hyundai Oilbank's Daesan plant. The project was pursued as a district energy business to provide a stable supply of electricity and steam to industrial facilities in the Daesan area of Seosan. The plant has a generation capacity of about 290 megawatts.
SNT Energy won the HRSG supply contract from Hyundai Engineering. The company said it carried out delivery and performance testing as planned.
An HRSG is a power generation facility that recovers high-temperature exhaust gas from gas turbines to produce steam. It improves energy efficiency and supplies steam needed by power plants and industrial facilities.
SNT Energy said the project reaffirmed its technological capabilities and execution track record in HRSG systems linked to mid-sized gas turbines, further strengthening its competitiveness in the power and energy plant market.
"Based on our accumulated technological competitiveness, we will further expand our position in the global HRSG market, beyond combined-cycle and industrial power generation markets at home and abroad," said Shin Kyung-in, chief executive officer of SNT Energy.